Analisis Faktor Keterlambatan COD Proyek PLN UIP Kalbagtim dengan Metode Analytical Hierarchy Process dan Fault Tree Analysis

Authors

  • Avira Dinda Pradiani Universitas Al Azhar Indonesia
  • Nunung Nurhasanah Universitas Al Azhar Indonesia

DOI:

https://doi.org/10.36722/sst.v6i1.639

Abstract

PLN Unit Induk Pembangunan Kalimantan Bagian Timur (PLN UIP Kalbagtim) is a company that is responsible for electricity needs in the East Kalimantan region. PLN UIP Kalbagtim covers three types of projects. There are power projects, substation projects, and transmission projects. However, many of these projects experienced delays in their Commercial Operation Date (COD). PLN UIP Kalbagtim only measures the risk level generally and does not measure the root causes of the possible occurrence of this risk. Based on these problems, a study was conducted to identify the projects that experienced delays the most using the Pareto diagram, then analyzed the factors and root causes of the delay using a fish-bone diagram, then using the Analytical Hierarchy Process method, data processing was done to obtain the probability value of each root event. Furthermore, using the Fault Tree Analysis method, the probability value of delay is calculated until the smallest value is found. From the research that has been done, it can be concluded that the transmission project in the form of SUTT is the project that most often experiences delays due to machine, man, material, method, and money factors. The factor that must be set as the priority or focus of the company is the money factor and the root of the incident in it will also be automatically deleted so that the possibility of delays is reduced from 52.71% to 25.28%. 

Keywords - Analytical Hierarchy Process, Fault Tree Analysis, Pareto Chart, Fish-bone Diagram


Author Biographies

Avira Dinda Pradiani, Universitas Al Azhar Indonesia

Program studi Teknik Industri, Fakultas Sains dan Teknologi

Nunung Nurhasanah, Universitas Al Azhar Indonesia

Program studi Teknik Industri, Fakultas Sains dan Teknologi

References

W. Y. Christina, D. Ludfi, and A. Thoyib, “Pengaruh Budaya Keselamatan Dan Kesehatan Kerja ( K3 ) Terhadap Kinerja Proyek Konstruksi,†J. Rekayasa Sipil, vol. 6, no. 1, pp. 83–95, 2012.

G. Y. Malingkas, T. T. Arsjad, and H. Tarore, “Menganalisis Sensitivitas Keterlambatan Durasi,†vol. 1, no. 9, pp. 603–607, 2013.

P. Pembangunan, J. Daniel, P. Tuelah, J. Tjakra, and D. R. O. Walangitan, “Peranan Konsultan Manajemen Konstruksi Pada Tahap Pelaksanaan Proyek Pembangunan (Studi Kasus : The Lagoon Taman Sari),†Tekno, vol. 12, no. 61, pp. 47–54, 2014.

R. Jani, “Bahan Baku Pakan Ternak Sapi Dalam Rangka Efisiensi Dengan Menggunakan Diagram Pareto, Metode EOQ Dan Diagram Sebab Akibat ( Studi Kasus Pada PT . Kariyana Gita Utama ),†2014.

A. Fendi, J. T. Industri, and F. T. Industri, “Analisis Strategi Mitigasi Risiko Pada Supply Chain Pt . Pal Indonesia ( PERSERO ) Pendahuluan Tantangan terbesar dalam proses produksi saat ini adalah mengelola dan mengurangi risiko Metodologi Penelitian Penelitian ini terbagi dalam 2 fase dalam House o,†Pros. Semin. Nas. Apl. Sains Teknol., no. ISSN: 1979-911X, pp. 1–10, 2012.

I. Z. Nasibu, “Penerapan Metode AHP Dalam Sistem Pendukung Keputusan Penempatan Karyawan Menggunakan Aplikasi Expert Choice,†2009.

D. R. Purwatiningsih, J. Teknik, I. Univeristas, and M. Malang, “Aplikasi Ahp Dalam pengambilan keputusan pada seleksi karyawan,†J. Tek. Ind., vol. 8, no. 11, p. 10, 2007.

I. Setyadi, “Analisis Penyebab Kecacatan Produk Celana Jeans Dengan Menggunakan Metode Fault Tree Analysis (Fta) Dan Failure Mode and Effect Analysis (Fmea) Di Cv Fragile Din Co,†pp. 1–78, 2013.

A. F. Mustika, “Analisa Keterlambatan Proyek Menggunakan Fault Tree Analysis ( Fta ) ( Studi Kasus Pada Proyek Pembangunan Gedung Program Studi Teknik Industri Tahap Ii Universitas Brawijaya Malang ) Naskah Publikasi Untuk Memenuhi Pesyaratan Memperoleh Gelar Sarjana Tek,†UNIVERSITAS BRAWIJAYA, 2014.

M. H. H. Hirzy Pradipta, Saifoe El Unas, “Analisa Kesehatan Dan Keselamatan Kerja Proyek Menggunakan Fault Tree Analysis (Fta) (Study Kasus Pada Proyek Jalan Hotmix Dinas Pekerjaan Umum Kabupaten Sumbawa),†J. Rekayasa dan Manaj. Sist. Ind., vol. 2, no. October, pp. 765–770, 2015.

L. Atika and R. J. Pusung, “Ipteks Pengelolaan Kas Kecil (Petty Cash) Pada Pt. Pln (Persero) Unit Induk Pembangunan Sulawesi Bagian Utara,†J. Ipteks Akunt. Bagi Masy., vol. 2, no. 02, pp. 370–373, 2018, doi: 10.32400/jiam.2.02.2018.21778.

Downloads

Published

2021-03-31

Issue

Section

JURNAL AL-AZHAR INDONESIA SERI SAINS DAN TEKNOLOGI